Letter dated, 24 October 2022

The Council's contractor, QMC Group, will start demolition and concrete works at the intersection of Church Street and Formosa Streets, Drummoyne,

Start date: 26 October 2022 (Wednesday)

Duration: 1 night (night works)

Working Hours: 7pm to 5am

The works will be carried out over one night. There will be minimal machinery noise which will cease at midnight and temporary restrictions to traffic. Access to Church Street will be temporarily closed during works and all roadway and footpath access will be reinstated at conclusion of night shift.

If there is inclement weather, QMC will try to start the work the next night. If unsuitable weather continues, QMC will update you on any changes to the schedule.

Thank you for your patience while we complete these important works.

More information

For more information, please contact Damien Marfutenko, on 0416 091 716 or at Damien.m@qmcgroup.com

Your sincerely,

Damien Marfutenko

Project Manager

Council contact: Andrew Goodsell, Coordinator City Projects P: (02) 9911 6555

QMC Group NSW Correspondence: Suite 208, 29-31 Lexington Drive Bella Vista NSW 2153 P: (02) 8882 8000