Night Works Notification: Kerb & Gutter Works

10 November 2022

This is an update from Council's contractor, QMC Group

Letter dated 10 November 2022

The Council’s contractor, QMC Group, will soon commence the demolition and re-install of concrete kerbs and gutters along Church Street, between Formosa Street and Victoria Road, Drummoyne. Where: Church Street, between Formosa Street and Victoria Road, Drummoyne

Type of work: Demolition and re-install of concrete kerb and gutters.

Start date: One night, Monday 14 th November 2022

Duration: 1 night (pending weather)

Working hours: 8pm to 5am

The works will be carried out over one night. There will be machinery noise and temporary restrictions to traffic. If there is inclement weather, QMC will try to start the work the next night. If unsuitable weather continues, QMC will update you on any changes to the schedule. Thank you for your patience while we complete these important works.

More information:

For more information, please contact Lyndon Toh, on 0416 091 714 or at lyndon@qmcgroup.com

Yours sincerely,

Lyndon Toh

Project Manager

QMC Group: NSW Correspondence: Suite 208, 29-31 Lexington Drive Bella Vista NSW 2153 P: (02) 8882 8000 / F: (02) 8882 8080

Council Contact: Council contact: Andrew Goodsell, Coordinator City Projects P: (02) 9911 6555