Project Background
We have proposed some upgrades to Utz Reserve, Drummoyne to make it a more accessible and inviting public space for the whole community to enjoy.
We consulted the community on the proposed concept.
Utz Reserve, Drummoyne is a small park with views across the Parramatta River to the Harbour Bridge. The proposed design responds to existing site conditions providing better access and seating in a landscaped garden setting.
The below table summary outlines the details of the initiation & planning phases of the project:
March 2022- December 2022 | Preliminary investigation to collapsed retaining wall. Installation of temporary shoring (timber structure) to damaged retaining wall. |
December 2022- May 2023 | Concept design preparation. Obtain structural certification to temporary shoring work and conduct remedial work (valid for 6 months). |
May 2023 – June 2023 | Concept design collaboration with the community. |
June 2023 – August 2023 | RFQ release to the market to engage design consultant, evaluation of submissions, and contract award. |
September 2023 – November 2023 | Obtain structural re-certification to temporary shoring work (valid for 6 months). Conduct Geotechnical Investigation to ascertain design. |
December 2023 – April 2024 | Obtain structural re-certification to temporary shoring work (valid for 6 months). Amend design based on Geotechnical findings. |
May 2024 – September 2024 | Obtain structural re-certification to temporary shoring work (valid for 6 months). Independent engineer review process to detailed design. |
September 2024 – February 2025 | Design finalisation. |
February 2025 - Current | Obtain structural re-certification to temporary shoring work (valid for 6 months). Commence delivery phase of project by preparing RFQ documents to obtain submissions from suitable civil / landscaping contractors. |
Next Steps
- Procurement of suitably qualified contractor to deliver project requirements in accordance with the final design.
- Construction commencement by June 2025.